Go To Past Projects Only

Ellisdale Construction Forest Ridge

todayAugust 14, 2023

Background
Ellisdale Forest

Forest Ridge Vistas Apartments

Location

Washington, DC

Owner/Client

Ellisdale Construction 

Participation Goals

Contracting Goals 

35% Certified Business Enterprise (CBE)  

Employment Goals 

20% Journey Worker Hours DC Residents    

60% Apprentice Hours DC Residents 

51% Skilled Laborer hours 

70% Common Laborer hours 

The Forest Ridge Vistas project is a restoration and renovation of affordable housing construction project. The project consists of 398 affordable rental units encompassing twenty-nine (29) two (2) and three (3) story residential buildings built between 1965 and 1968. Located in Southeast Washington, DC, this project is being constructed by Ellisdale Construction, selected by the Developer, as the General Contractor.  

L.S. Caldwell & Associates, Inc. (LSC) is charged with Compliance oversight for the project.  LSC will serve as the liaison between the Department of Employment Services (DOES), the Department of Small and Local Business Department (DSLBD), the Developer and Project Contractors to ensure that CBE and Employment participation requirements are achieved.

Specific strategies established to reinforce compliance conformance include:

WORKFORCE PARTICIPATION MONITORING

  • Obtained payroll data from LCP Tracker; compile bi-weekly and cumulative workforce diversity data.
  • Analyzed construction workforce diversity data to highlight results, trends and identify risks.
  • Coordinated with representatives of the building trades, as appropriate. 
  • Performed site visits periodically to verify workforce participation. 
  • Attended project meetings bi-weekly, or as otherwise requested. 

CONTRACT PARTICIPATION MONITORING

  • Analyzed M/W/DSBE participation data, comparing commitment to actual payment made to M/W/DSBEs. 
  • Tracked payments to contractors/subcontractors and monitoring actual payments relative to goals. 
  • Submitted contract participation reports monthly. 
  • Performed site visits and contacting the grantee, contractors, subcontractors, and other City departments as necessary to verify contract participation. 

STRATEGIES FOR SUCCESS

  • Monitored contractor compliance through frequent communication, data collection, site visits and participation in project meetings, as necessary. 
  • Identified, investigating, reporting and resolving discrepancies in the data, as necessary. 
  • Evaluated contractor’s compliance with contract goals.   
  • Provided advice to the Client on actions to be taken in the event of non-compliance and on the pros and cons of alternative actions. 

Written by: QueveraAdmin